The UK’s first interconnector with Germany gains European funding

Electrical Review Logo

Construction on the UK’s first interconnector with Germany is expected to start this year, with the European Investment Bank committing to funding the project. 

The European Investment Bank is set to stump up €400 million for the financing of the European part of the project, which will go some way to providing the funding necessary to build the connector, which is estimated to cost in the region of €2.8 billion.

Thankfully, the European Investment Bank isn’t the only bank providing cash towards the project. In fact, the NeuConnect interconnector will be well funded. A consortium of more than 20 banks including the EIB, the UK Infrastructure Bank and the Japan Bank for International Cooperation (JBIC) will support investors Meridiam, Allianz Capital Partners, and Kansai Electric Power in this €2.8 billion investment.

The project will be the first interconnector between Germany and the United Kingdom, facilitating electricity trade between the European Union and the United Kingdom and contributing to the integration of high shares of intermittent renewables across the North Sea. The expected start date of commercial operations is in 2028.

The project consists of a high-voltage direct current link interconnecting England and Germany through German, Dutch and British waters. The project will have a rated capacity of 1400 MW and DC voltage of 525 kV. The predominantly subsea cable will have a route length of 725 km and will connect a converter station and German grid interface to Tennet’s electricity network near Fedderwarden, and a converter station and grid interface on the Isle of Grain in the United Kingdom to the National Grid ESO network.

The project is an example of mutually beneficial cooperation between the European Union and the United Kingdom, including cross-border environmental benefits.

Siemens has been appointed as the contractor for the converter stations, and Prysmian will manufacture and install the cable. 

The interconnector will help to ensure better utilisation of offshore wind capacities on the coasts according to the respective local wind strength, thereby supporting EU and German renewable energy policies. The project will make it possible to reduce CO2 emissions and will contribute to meeting the European greenhouse gas emission reduction target of at least 55% by 2030.

The route of the project will be implemented entirely underground and under the sea, meaning that the project does not fall under Annex I or Annex II of the Environmental Impact Assessment (EIA) Directive. Environmental impact studies have been carried out and appropriate measures will be taken to avoid, mitigate and compensate for the impacts.

Ambroise Fayolle, Vice President of the European Investment Bank, noted, “This project is ground-breaking for the energy transition, as it makes it possible to use offshore wind energy more efficiently. Cross-border electricity trade can help redirect power to where it is most needed, and can thus contribute to the integration of renewables and the stability of the energy supply.”

Top Stories

Join the Electrical Review Community

Electrical Review is the go-to source for electrical engineers, with more than 150 years of dedication to the industry.


© SJP Business Media.

Stay In The Know

Sign up to receive the Electrical Review Newsletter, the Digital Issue of the Electrical Review Magazine and be the first to hear about the latest events from us.