Skip to content Skip to footer

Solar salvation

Electrical Review Logo

Photon Energy has installed ground breaking solar plus storage at Prologis Park Pineham, not only allowing the building to run on self-generated electricity, but potentially saving up to 54 tonnes of CO2 emissions annually.

Photon Energy has recently completed a sizeable solar plus storage installation at a grade ‘A’ distribution centre, located on Prologis Park, Pineham.

This new state-of-the-art development, built by Buckingham Group was completed towards the end of 2018. Lewis & Beddows, a local mechanical and electrical contractor responsible for the building services, awarded Photon Energy the contract to install the solar and storage system. 

By installing a cluster of batteries alongside the solar array, this pilot project is hoping to see the building’s occupiers being able to use a large percentage of self-generated electricity on site.

Careful consideration went into the design of the 19,630m² building to achieve the maximum level of energy efficiency (a grade A energy performance rating) and this was attained through a number of measures. 

Passive design elements such as high levels of insulation and airtightness were incorporated alongside the installation of the most energy efficient building services and the 130 kWp solar PV array.

The solar PV array installed by Photon Energy was comprised of Trina 270kWp modules and a stack of 4 Tesla Powerwalls, designed to have a total of 56kWh capacity. The modules were fixed to the steel trapezoidal roof using a K2 SpeedRail system.

The Solis inverters were positioned in the main office plant deck, with cabling routed to minimise penetrations through the façade.

The solar PV will generate approximately 104,110kWh of electricity each year for the building’s occupiers, with the batteries ensuring the minimal amount is returned to the national grid. The renewable energy generated should save approximately 54 tonnes of CO₂ emissions per annum.

Lefteris Giraleas, senior engineer at Photon Energy said, “It’s very encouraging to know that all the electricity generated by the solar PV will be used on site to help reduce the operating centre’s carbon emissions.”

Steve Ward, project manager at Lewis & Beddows added, “It was a pleasure working with Photon Energy on this ground-breaking solar plus storage project. Scott was one of the best on site engineers I have worked with and on any further projects I would be requesting his attendance.”

 

Top Stories

Stay In The Know

Get the Electrical Review Newsletter direct to your inbox, and don't miss a thing.