Further UPS installations at Reading
Uninterruptible Power Supply (UPS) specialist, Borri has just completed the installation and commissioning of four additional, high efficiency Borri B9600FXS UPS units at Everest Data Centre’s facility in Reading.
The Borri B9600FXS UPS modules have been positioned in a 2N electrical configuration, where one has been custom designed in orange and another in black to identify the A + B supplies. All associated switchgear and cabling have also been custom coloured respectively.
This additional 1.6MVA in emergency power capacity has been installed to support the rapidly expanding co-located data centre, which due to demand has accelerated its expansion plans and space continues to go fast.
Everest Data Centre’s owner, Ed Butler commented on the recent works: “The uptake of
Borri
0800 136 993
Recommended Reading
.jpg%3F2026-08-24T08%253A44%253A01.948Z&w=3840&q=100)
UK Government launches £28m challenge for 100-hour energy storage
The Government is backing electrochemical and hydrogen storage technologies designed to supply energy over periods of at least 100 hours.

Parliamentary petition seeks to limit BESS installations to AI Growth Zones
A proposed BESS moratorium outside AI Growth Zones risks treating grid-scale storage as an adjunct to data centres, not critical infrastructure.

Aura Power and Verdant merge to create 1GW solar and battery platform
Aura Power and Verdant Energy have merged to form a UK solar and battery IPP with 1GW operating or under construction and a 10GW pipeline.